Dec qtr 23 ($m) | Sep qtr 23 to Dec qtr 23 (%) | Dec qtr 22 to Dec qtr 23 (%) | |
---|---|---|---|
For the private sector | 17,007.6 | 2.0 | 13.8 |
For the public sector (b) | 14,659.7 | 6.6 | 21.2 |
Total engineering construction | 31,667.4 | 4.1 | 17.1 |
- Reference year for chain volume measures is 2021-22.
- Includes work done by the private sector for the public sector and work done by the public sector.
Dec qtr 23 ($m) | Sep qtr 23 to Dec qtr 23 (%) | Dec qtr 22 to Dec qtr 23 (%) | |
---|---|---|---|
For the private sector | 16,998.2 | 1.1 | 11.7 |
For the public sector (b) | 14,406.0 | 4.0 | 17.4 |
Total engineering construction | 31,404.2 | 2.4 | 14.3 |
- Reference year for chain volume measures is 2021-22.
- Includes work done by the private sector for the public sector and work done by the public sector.
a. Reference year for chain volume measures is 2021-22.
a. Reference year for chain volume measures is 2021-22.
Value of work done, chain volume measures
Total
The seasonally adjusted estimate for the value of total engineering construction work done rose 4.1% in the December quarter to $31,667.4m. The trend estimate rose 2.4%.
Private Sector
The seasonally adjusted estimate for the value of work done for the private sector rose 2.0% in the December quarter to $17,007.6m. The trend estimate rose 1.1%.
Public Sector
The seasonally adjusted estimate for the value of work done for the public sector rose 6.6% in the December quarter to $14,659.7m. The trend estimate rose 4.0%.