MARCH KEY FIGURES
| | Mar qtr 04 | Dec qtr 03 to Mar qtr 04 | Mar qtr 03 to Mar qtr 04 | |
| | $m | % change | % change | |
TREND ESTIMATES VOLUME TERMS(a) | |
| |
Value of work done | | | | |
| For the private sector | 3,851.8 | 3.4 | 14.7 | |
| For the public sector(b) | 2,701.1 | 0.9 | -2.8 | |
| Total engineering construction | 6,543.8 | 2.2 | 6.6 | |
SEASONALLY ADJUSTED VOLUME TERMS(a) | |
| |
Value of work done | | | | |
| For the private sector | 3,841.4 | 0.3 | 11.7 | |
| For the public sector(b) | 2,757.1 | 4.0 | 1.8 | |
| Total engineering construction | 6,598.5 | 1.8 | 7.4 | |
| |
(a) Chain volume measures, reference year 2001-02. |
(b) Includes work done by the private sector for the public sector and work done by the public sector. |
Value of work done, Total engineering - Volume terms
| Value of work done, Volume terms - Trend estimates
|
MARCH KEY POINTS
VALUE OF CONSTRUCTION WORK DONE, VOLUME TERMS
Trend estimates
- The trend estimate for the value of total engineering construction work done rose 2.2% in the March 2004 quarter. The estimate has now risen for twelve successive quarters.
- The trend estimate for the value of work done for the private sector rose 3.4% in the March 2004 quarter, the tenth consecutive quarterly rise. Work done for the public sector rose 0.9% in the March 2004 quarter.
Seasonally adjusted estimates
- The seasonally adjusted estimate for the value of total engineering construction work done in the March 2004 quarter rose 1.8%, to $6,598.5m. This is the highest estimate since the current series began in the September quarter 1986.
- The seasonally adjusted estimate for the value of work done for the private sector rose 0.3%, to $3,841.4m in the March 2004 quarter. The value of work done for the public sector rose 4.0%, to $2,757.1m.
Original estimates
- The value of work done in the March 2004 quarter fell 6.8%, to $6,192.6m, following an 11.3% rise in the December quarter 2003.
- The value of work done for the private sector fell 9.4%, to $3,594.0m in the March quarter 2004 following the record estimate of $3,966.9m in the December quarter. The value of work done for the public sector fell 3.0%, to $2,598.6m, following a 13.2% rise in the December quarter.
NOTES
FORTHCOMING ISSUES
ISSUE (QUARTER) | Release Date |
June 2004 | 12 October 2004 |
September 2004 | 20 January 2005 |
CHANGES IN THIS ISSUE
Commencing from this issue, there will be two additional tables (tables 3 & 4) containing chain volume data for the value of work done by states and territories. All subsequent tables have been renumbered.
SIGNIFICANT REVISIONS THIS QUARTER
Revisions have been made to the September and December 2003 quarter estimates of work commenced, work done and work yet to be done for 'electricity generation, transmission and distribution'. For the September quarter 2003, estimates have been revised upwards by $78.0m for work commenced, $19.0m for work done and $120.7m for work yet to be done. For the December quarter 2003, estimates have been revised upwards by $9.7m for work commenced, $37.6m for work done and $94.1m for work yet to be done.
DATA NOTES
There are no notes about the data.
INQUIRIES
For further information about these and related statistics, contact the National Information and Referral Service on 1300 135 070 or Andrew Stidston on Adelaide (08) 8237 7668.