8762.0 - Engineering Construction Activity, Australia, Dec 2010 Quality Declaration 
ARCHIVED ISSUE Released at 11:30 AM (CANBERRA TIME) 05/04/2011   
   Page tools: Print Print Page Print all pages in this productPrint All

DECEMBER KEY FIGURES

Dec qtr 10
Sep qtr 10 to Dec qtr 10
Dec qtr 09 to Dec qtr 10
$m
% change
% change

TREND ESTIMATES(a)

Value of work done
For the private sector
13 777.9
5.3
15.7
For the public sector(b)
7 284.1
-0.3
-2.9
Total engineering construction
21 013.2
3.0
8.2

SEASONALLY ADJUSTED ESTIMATES(a)

Value of work done
For the private sector
14 134.2
10.7
21.1
For the public sector(b)
7 445.4
4.9
3.8
Total engineering construction
21 579.6
8.6
14.5

(a) Chain volume measures, reference year 2008-09.
(b) Includes work done by the private sector for the public sector and work done by the public sector.

Value of work done, Chain volume measures
Graph: Value of work done, Chain volume measures

Value of work done, Chain volume measures - Trend estimates
Graph: Value of work done Volume terms Trend estimates




DECEMBER KEY POINTS


VALUE OF WORK DONE, CHAIN VOLUME MEASURES

TOTAL
  • The trend estimate for the value of total engineering construction work done rose 3.0% in the December 2010 quarter.
  • The seasonally adjusted estimate for the value of total engineering construction work done rose 8.6% in the December quarter, to $21,579.6m.


PRIVATE SECTOR
  • The trend estimate for the value of work done for the private sector rose 5.3% in the December quarter.
  • The seasonally adjusted estimate for the value of work done for the private sector rose 10.7% in the December quarter, to $14,134.2m.


PUBLIC SECTOR
  • The trend estimate for the value of work done for the public sector fell 0.3% in the December quarter.
  • The seasonally adjusted estimate for the value of work done for the public sector rose 4.9% in the December quarter, to $7,445.4m.


VALUE OF WORK COMMENCED, CURRENT PRICES
  • The value of work commenced in the December quarter was $28,759.6m, an increase of 60.2% from the September quarter.


NOTES

FORTHCOMING ISSUES

ISSUE (QUARTER) Release Date
March 2011 6 July 2011
June 2011 5 October 2011



ABOUT THIS ISSUE

This publication updates the preliminary estimates released in Construction Work Done, Australia (cat. no. 8755.0) on 23 February 2011.


CHANGES IN THIS ISSUE

No changes in this issue.


SIGNIFICANT REVISIONS THIS QUARTER

Compared with the current price estimates in original terms published in the previous issue of this publication:
  • The September quarter work done estimates have been revised down by $112.2m. These revisions occurred predominantly in the Roads, highways and subdivisions and Sewerage and Drainage commodities.


DATA NOTE

Widespread flooding in the eastern states, particularly Queensland, and other recent natural disasters have not affected the quality of statistics in this release. As these events occurred after, or very late, in the December quarter reference period, the overall level of construction activity was not noticeably affected for either national or state level estimates.


INQUIRIES

For further information about these and related statistics, contact the National Information and Referral Service on 1300 135 070.