JUNE KEY FIGURES
| | Jun Qtr 15 | Mar Qtr 15 to Jun Qtr 15 | Jun Qtr 14 to Jun Qtr 15 |
| | $m | % change | % change |
|
Trend estimates(a) | | | |
| Total new capital expenditure | 34 513 | -3.9 | -10.0 |
| Buildings and structures | 21 884 | -5.3 | -15.6 |
| Equipment, plant and machinery | 12 714 | -0.8 | 2.4 |
Seasonally adjusted(a) | | | |
| Total new capital expenditure | 34 341 | -4.0 | -10.5 |
| Buildings and structures | 21 689 | -5.6 | -16.7 |
| Equipment, plant and machinery | 12 655 | -1.2 | 2.8 |
|
(a) In volume terms |
New Capital Expenditure, in volume terms
| |
JUNE KEY POINTS
ACTUAL EXPENDITURE (VOLUME TERMS)
- The trend volume estimate for total new capital expenditure fell 3.9% in the June quarter 2015 while the seasonally adjusted estimate fell 4.0%.
- The trend volume estimate for buildings and structures fell 5.3% in the June quarter 2015 while the seasonally adjusted estimate fell 5.6%.
- The trend volume estimate for equipment, plant and machinery fell 0.8% in the June quarter 2015 while the seasonally adjusted estimate fell 1.2%.
EXPECTED EXPENDITURE (CURRENT PRICE TERMS)
- This issue includes the seventh estimate (Estimate 7) for 2014-15 and the third estimate (Estimate 3) for 2015-16.
- Estimate 7 for 2014-15 is $150,579m. This is 4.7% lower than Estimate 7 for 2013-14. Estimate 7 is 0.5% higher than Estimate 6 for 2014-15.
- Estimate 3 for 2015-16 is $114,814m. This is 23.4% lower than Estimate 3 for 2014-15. Estimate 3 is 9.9% higher than Estimate 2 for 2015-16.
- See pages 7-10 for further commentary on expectations data.
NOTES
FORTHCOMING ISSUES
ISSUE (QUARTER) | Release Date |
September 2015 | 26 November 2015 |
December 2015 | 25 February 2016 |
March 2016 | 26 May 2016 |
June 2016 | 25 August 2016 |
CHANGES TO THIS ISSUE
- No changes to this issue.
INQUIRIES
Inquiries about these and related statistics, contact the National Information and Referral Service on 1300 135 070. The ABS Privacy Policy outlines how the ABS will handle any personal information that you provide to us.