VALUE OF WORK DONE STATES AND TERRITORIES


CHAIN VOLUME MEASURES - TREND ESTIMATES


NEW SOUTH WALES

Graph: NSW, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 3.5% in the March quarter and has risen for six quarters.


VICTORIA
Graph: Vic, value of work done, trend estimates, chain volume measures

The trend estimate of the value of work done rose 1.1% in the March quarter and has risen for five quarters.


QUEENSLAND
Graph: Qld, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 2.1% in the March quarter, continuing the period of strong growth since December 2003 quarter.


SOUTH AUSTRALIA
Graph: SA, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 5.7% in the March quarter and has risen for five quarters.


WESTERN AUSTRALIA
Graph: WA, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done fell by 0.6% in the March quarter after showing growth since March 2004.


TASMANIA
Graph: Graph Tas, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done is now showing a fall 6.4% in the March quarter after rising for three quarters.


NORTHERN TERRITORY
Graph: NT, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 7.7% in the March quarter and has risen for five quarters.


AUSTRALIAN CAPITAL TERRITORY
Graph: ACT, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done fell 2.4% in the March quarter and has fallen for two quarters.