8762.0 - Engineering Construction Activity, Australia, Jun 2009 Quality Declaration 
ARCHIVED ISSUE Released at 11:30 AM (CANBERRA TIME) 01/10/2009   
   Page tools: Print Print Page Print all pages in this productPrint All

VALUE OF WORK DONE STATES AND TERRITORIES


CHAIN VOLUME MEASURES - TREND ESTIMATES


NEW SOUTH WALES

Graph: NSW, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 1.5% in the June quarter and has risen for seven quarters.


VICTORIA
Graph: Vic, value of work done, trend estimates, chain volume measures

The trend estimate of the value of work done rose 3.9% in the June quarter and has risen for six quarters.


QUEENSLAND
Graph: Qld, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 1.4% in the June quarter, continuing the period of strong growth since December 2003 quarter.


SOUTH AUSTRALIA
Graph: SA, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 11.8% in the June quarter and has risen for six quarters.


WESTERN AUSTRALIA
Graph: WA, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose by 3.3% in the June quarter and is now showing growth since June 2004.


TASMANIA
Graph: Graph Tas, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done fell by 11.8% in the June quarter and has fallen for two quarters.


NORTHERN TERRITORY
Graph: NT, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 1.5% in the June quarter and has risen for six quarters.


AUSTRALIAN CAPITAL TERRITORY
Graph: ACT, value of work done, trend estimates, chain volume measures

The trend estimate for the value of work done rose 0.7% in the June quarter after falling for two quarters.